PRINCE2 Agile Foundation Practice Questions 2025 – The All-in-One Guide to Exam Success!

Question: 1 / 400

What principle from PRINCE2 Agile is being applied by learning from previous campaigns?

Manage by Exception

Learn from Experience

The principle that is being applied by learning from previous campaigns is about continuously improving and adapting by reflecting on past experiences. This concept emphasizes the importance of gathering insights and lessons learned from previous projects or campaigns to enhance future performance. By analyzing what worked well and what did not, teams can make informed decisions and implement strategies that build on their successes while avoiding past mistakes.

In the context of PRINCE2 Agile, learning from experience involves not only documenting lessons learned but also integrating those learnings into the planning and executing phases of future projects. This principle encourages a culture of reflection and adaptability, which is vital in agile environments where client needs and market conditions can change rapidly.

The other principles, while important in their own right, focus on different aspects of project management. For instance, managing by exception relates to allowing more focus on significant deviations from the plan rather than day-to-day management, while embracing change highlights the value of being responsive to changes rather than rigidly adhering to initial plans. Focusing on products underscores the importance of delivering quality outputs that meet stakeholder expectations. Each of these principles contributes to effective project management in various ways, but the specific action of learning from past experience aligns directly with the second principle.

Get further explanation with Examzify DeepDiveBeta

Embrace Change

Focus on Products